WPPP Unit 1 and 2 HRSG Foundation

Bunney’s inc was able to successfully complete the Unit 1 and 2 concrete foundations additions during a tight window for APS. Again Bunney’s inc safety was exceptional on this project with no recordables or injuries. The team was able to successful dowel over 250 #8 rebar into the existing foundation and pour over 280 yards in a 4 day period. The team was efficient and allowed APS to load the structure 4 days ahead of schedule due to Bunney’s ability to complete the work without rework and passing all inspections on the first try. The client was extremely pleased with Bunney’s attention to detail and quality of work on this project.